PrepAway - Latest Free Exam Questions & Answers

Who, along with the project manager, is supposed to direct the performance…?

Who, along with the project manager, is supposed to direct the performance of the
planned project activities and manage the various technical and organizational
interfaces that exist within the project?

PrepAway - Latest Free Exam Questions & Answers

A.
The customer and functional managers

B.
The risk owners and stakeholders

C.
The sponsors and stakeholders

D.
Theproject management team