which process in Project Cost Management?

The cost baseline and project funding requirements are outputs of which process in
Project Cost Management?

PrepAway - Latest Free Exam Questions & Answers

A.
Estimate Costs

B.
Control Costs

C.
Plan Cost Management

D.
Determine Budget