PrepAway - Latest Free Exam Questions & Answers

An output of the Direct and Manage Project Work process is:

An output of the Direct and Manage Project Work process is:

PrepAway - Latest Free Exam Questions & Answers

A.
Deliverables.

B.
Activity lists.

C.
A work breakdown structure.

D.
A scope statement.