Which of the following is an output of the Monitor and Control Project Work process?

Which of the following is an output of the Monitor and Control Project Work
process?

PrepAway - Latest Free Exam Questions & Answers

A.
Change requests

B.
Performance reports

C.
Organizational process assets

D.
Project management plan