What process determines which risks might affect the project?

What process determines which risks might affect the project?

PrepAway - Latest Free Exam Questions & Answers

A.
Qualitative risk analysis

B.
Identify Risks

C.
Plan Risk Management

D.
Quantitative risk analysis