Yourproject has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80
work days. What should be your concern?
A.
There is a cost under run.
B.
There is a cost overrun.
C.
May not meet deadline.
D.
The project is 20 days behind schedule.