PrepAway - Latest Free Exam Questions & Answers

What should be your concern?

Yourproject has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80
work days. What should be your concern?

PrepAway - Latest Free Exam Questions & Answers

A.
There is a cost under run.

B.
There is a cost overrun.

C.
May not meet deadline.

D.
The project is 20 days behind schedule.


Leave a Reply