what is the schedule performance index (5PI) for Task 4?

The following chart contains information about the tasks in a project.

Based on the chart, what is the schedule performance index (5PI) for Task 4?

PrepAway - Latest Free Exam Questions & Answers

A.
0.83

B.
0.9

C.
1.11

D.
1.33