PrepAway - Latest Free Exam Questions & Answers

what is the cost performance index (CPI) for Task 2?

The following chart contains information about the tasks in a project.

Based on the chart, what is the cost performance index (CPI) for Task 2?

PrepAway - Latest Free Exam Questions & Answers

A.
0.8

B.
1

C.
1.25

D.
1.8


Leave a Reply