In which process group is the scope first defined?
A. Initiating
B. Planning
C. Executing
D. Controlling
2 Comments on “which process group is the scope first defined?”
Sarahsays:
No B (planning)
0
0
Jay Teesays:
Answer is A.
Justification: PMBok Guide version 5- pg 424.
Paragraph 1 from line 2, “…Within the Initiating processes, the initial scope is defined and initial financial resources are committed…”
No B (planning)
0
0
Answer is A.
Justification: PMBok Guide version 5- pg 424.
Paragraph 1 from line 2, “…Within the Initiating processes, the initial scope is defined and initial financial resources are committed…”
0