What should be the concern?

A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80
workdays. What should be the concern?

PrepAway - Latest Free Exam Questions & Answers

A.
Thereis a cost underrun.

B.
Thereis a cost overrun.

C.
The project may not meet the deadline.

D.
Theproject is 20 days behind schedule.