Which Project Management Process Group includes Collect Requirements, Define Activities…?

Which Project Management Process Group includes Collect Requirements, Define
Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform
Quantitative Risk Analysis?

PrepAway - Latest Free Exam Questions & Answers

A.
Initiating

B.
Monitoring and Controlling

C.
Planning

D.
Closing