Which of the following is an output of the Perform Integrated Change Control process?

Which of the following is an output of the Perform Integrated Change Control
process?

PrepAway - Latest Free Exam Questions & Answers

A.
Project document updates

B.
Organizational process assets updates

C.
Change requests

D.
Deliverables