Which of the following Project Communication Management processes uses performance reports as an input?

Which of the following Project Communication Management processes uses
performance reports as an input?

PrepAway - Latest Free Exam Questions & Answers

A.
Manage Stakeholder Expectations

B.
Report Performance

C.
Distribute Information

D.
Plan Communications