Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start

A project manager at a publishing company decides to initiate the editing phase of
the project as soon as each chapter is written. Which type of Sequence Activities
tool and technique is involved, considering that there was a start-to-start
relationship with a 15-day delay?

PrepAway - Latest Free Exam Questions & Answers

A.
Slack

B.
Float

C.
Lag

D.
Lead