Which process involves subdividing project deliverables and project work into smaller, more manageable portion

Which process involves subdividing project deliverables and project work into
smaller, more manageable portions?

PrepAway - Latest Free Exam Questions & Answers

A.
Develop Schedule

B.
Create VVBS

C.
Estimate Activity Resources

D.
Define Scope