PrepAway - Latest Free Exam Questions & Answers

Which of the following is the primary output of the Identify Risks process?

Which of the following is the primary output of the Identify Risks process?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk management plan

B.
Risk register

C.
Change requests

D.
Risk response plan


Leave a Reply