The process of prioritizing risks for further analysis or action is known as:

The process of prioritizing risks for further analysis or action is known as:

PrepAway - Latest Free Exam Questions & Answers

A.
Plan Risk Management.

B.
Plan Risk Responses.

C.
Perform Qualitative Risk Analysis.

D.
Perform Quantitative Risk Analysis.