Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

Which Collect Requirements output links the product requirements to the
deliverables that satisfy them?

PrepAway - Latest Free Exam Questions & Answers

A.
Requirements documentation

B.
Requirements traceability matrix

C.
Project management plan updates

D.
Project documents updates