A project manager should document the escalation path for unresolved project risks in the:

A project manager should document the escalation path for unresolved project risks
in the:

PrepAway - Latest Free Exam Questions & Answers

A.
Change control plan

B.
Stakeholder register

C.
Risk log

D.
Communications management plan