A risk response strategy in which the project team shifts the impact of a threat, together with ownership of t

A risk response strategy in which the project team shifts the impact of a threat,
together with ownership of the response, to a third party is called:

PrepAway - Latest Free Exam Questions & Answers

A.
mitigate

B.
accept

C.
transfer

D.
avoid