Which tools are at the manager’s disposal?

The project manager at an organization has just realized that some of the
engineering staff has been allocated to project Y and will not be available to finish
task X. The project manager has also discovered that at the current pace, it will not
be possible to complete the project on time. Due to cost constraints, hiring more
work force is not a viable option. Which tools are at the manager’s disposal?

PrepAway - Latest Free Exam Questions & Answers

A.
Resource leveling and fast tracking

B.
Fast tracking and crashing

C.
Crashing and applying leads and lags

D.
Scheduling tools and applying leads and lags