Which of the following outputs from the Control Schedule process aids in the communication…?

Which of the following outputs from the Control Schedule process aids in the
communication of schedule variance (SV), schedule performance index (SPI), or any
performance status to stakeholders?

PrepAway - Latest Free Exam Questions & Answers

A.
Performance organizations

B.
Schedule baselines

C.
Work performance measurements

D.
Change requests