Which action is included in the Control Costs process?

Which action is included in the Control Costs process?

PrepAway - Latest Free Exam Questions & Answers

A.
Identify how the project costs will be planned, structured, and controlled

B.
Determine policies, objectives, and responsibilities to satisfy stakeholder needs

C.
Develop an approximation of the monetary resources needed to complete project
activities

D.
Monitor cost performance to isolate and understand variances from the approved
cost baseline