PrepAway - Latest Free Exam Questions & Answers

Which of the following factors is lowest at the start of the project?

Which of the following factors is lowest at the start of the project?

PrepAway - Latest Free Exam Questions & Answers

A.
Cost of changes

B.
Stakeholder influences

C.
Risk

D.
Uncertainty