Which output is the approved version of the time-phased project budget?

Which output is the approved version of the time-phased project budget?

PrepAway - Latest Free Exam Questions & Answers

A.
Resource calendar

B.
Scope baseline

C.
Trend analysis

D.
Cost baseline