Whatis the actual cost of the project?

The CPI is .92, and the EV is US$172,500.Whatis the actual cost of the project?

PrepAway - Latest Free Exam Questions & Answers

A.
US$158,700

B.
US$172,500

C.
US$187,500

D.
US$245,600