which project management process?

Approved change requests, approved corrective actions, and updates to
organizational process assets are all outputs of which project management process?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk response planning

B.
Manage stakeholders

C.
Scope definition

D.
Performance reporting