Which of the following can result from fast tracking?

Fast tracking is a schedule compression technique used to shorten the project
schedule without changing project scope. Which of the following can result from fast
tracking?

PrepAway - Latest Free Exam Questions & Answers

A.
The risk of achieving the shortened project time is increased.

B.
The critical path will have positive total float.

C.
Contingency reserves are released for redeployment by the project manager.

D.
Duration buffers are added to maintain a focus on planned activity durations.