What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150,

What is the schedule performance index (SPI) if the planned value (PV) is $100, the
actual cost (AC) is $150, and the earned value (EV) is $50?

PrepAway - Latest Free Exam Questions & Answers

A.
0.50

B.
0.67

C.
1.50

D.
2.00