Which of the following includes how requirements activities will be planned, tracked, and reported?

Which of the following includes how requirements activities will be planned,
tracked, and reported?

PrepAway - Latest Free Exam Questions & Answers

A.
Configuration management plan

B.
Scope baseline

C.
Requirements management plan

D.
Schedule baseline