What was the original budget at completion for the project?

The project has a current cost performance index of 0.80. Assuming this
performance wi continue, the new estimate at completion is $1000. What was the
original budget at completion for the project?

PrepAway - Latest Free Exam Questions & Answers

A.
$800

B.
$1000

C.
$1250

D.
$1800