which process would you obtain stakeholders’ formal acceptance of the completed project scope?

During which process would you obtain stakeholders’ formal acceptance of the
completed project scope?

PrepAway - Latest Free Exam Questions & Answers

A.
Quality control

B.
Scope verification

C.
Scope control

D.
Close project