Which process involves monitoring the status of the project to update the project costs and managing changes t

Which process involves monitoring the status of the project to update the project
costs and managing changes to the cost baseline?

PrepAway - Latest Free Exam Questions & Answers

A.
Estimate Costs

B.
Control Costs

C.
Determine Budget

D.
Plan Cost Management