Which schedule method allows the project team to place buffers on the project schedule path to account for lim

Which schedule method allows the project team to place buffers on the project
schedule path to account for limited resources and project uncertainties?

PrepAway - Latest Free Exam Questions & Answers

A.
Critical path method

B.
Critical chain method

C.
Resource leveling

D.
Schedule network analysis