PrepAway - Latest Free Exam Questions & Answers

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $5

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100,
the actual cost (AC) is $50, and the earned value (EV) is $25?

PrepAway - Latest Free Exam Questions & Answers

A.
$50

B.
$100

C.
$125

D.
$200

Explanation:
EAC=BAC/CPI and CPI=EV/AC
CPI = EV/ AC = 25/50 = 0.5
EAC = BAC/ CPI = 100/0.5 = $200

One Comment on “What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $5


Leave a Reply