which document?

A projects purpose or justification, measurable project objectives and related
success criteria, a summary milestone schedule, and a summary budget are all
components of which document?

PrepAway - Latest Free Exam Questions & Answers

A.
Workbreakdown structure

B.
Requirements document

C.
Project charter

D.
Project management plan