In the Estimate Activity Durations process, productivity metrics and published commercial information inputs a

In the Estimate Activity Durations process, productivity metrics and published
commercial information inputs are part of the:

PrepAway - Latest Free Exam Questions & Answers

A.
enterprise environmental factors.

B.
organizational process assets.

C.
project management plan,

D.
project funding requirements.