Scope, schedule, and cost parameters are integrated in the:

Scope, schedule, and cost parameters are integrated in the:

PrepAway - Latest Free Exam Questions & Answers

A.
Performance measurement baseline.

B.
Analysis of project forecasts,

C.
Summary of changes approved in a period,

D.
Analysis of past performance.