PrepAway - Latest Free Exam Questions & Answers

What are the formal and informal policies, procedures, and guidelines that could impact how the project’

What are the formal and informal policies, procedures, and guidelines that could
impact how the project’s scope is managed?

PrepAway - Latest Free Exam Questions & Answers

A.
Organizational process assets

B.
Enterprise environmental factors

C.
Project management processes

D.
Project scope management plan