Which of the following strategies is used to deal with risks that may have a negative impact on project object

Which of the following strategies is used to deal with risks that may have a negative
impact on project objectives?

PrepAway - Latest Free Exam Questions & Answers

A.
Exploit

B.
Share

C.
Enhance

D.
Transfer