Budgets reserved for unplanned changes to project scope and cost are:
A. Contingency reserves.
B. Management reserves.
C. Authorized budgets.
D. Cost baselines.
One Comment on “Budgets reserved for unplanned changes to project scope and cost are:”
Nasr Aghasays:
WRONG!. Management Reserves are “for unforeseen work that IS within Scope of the project”. They are not for unplanned changes. Anyway, changes are NOT usually planned!!!
WRONG!. Management Reserves are “for unforeseen work that IS within Scope of the project”. They are not for unplanned changes. Anyway, changes are NOT usually planned!!!