which part of the plan will this type of information be included?

While preparing the project management plan on a weekly basis, the project
manager indicates the intention to provide an issues report to the staff via e-mail. In
which part of the plan will this type of information be included?

PrepAway - Latest Free Exam Questions & Answers

A.
Communications management plan

B.
Human resource plan

C.
Quality management plan

D.
Procurement management plan