PrepAway - Latest Free Exam Questions & Answers

Which of the following schedule network analysis techniques is applied when a critical path method calculation

Which of the following schedule network analysis techniques is applied when a
critical path method calculation has been completed and resources availability is
critical?

PrepAway - Latest Free Exam Questions & Answers

A.
Applying calendars

B.
Resource leveling

C.
Resource planning

D.
Resource conflict management


Leave a Reply