PrepAway - Latest Free Exam Questions & Answers

An input to the Perform Integrated Change Control process is:

An input to the Perform Integrated Change Control process is:

PrepAway - Latest Free Exam Questions & Answers

A.
expert judgment

B.
seller proposals

C.
the project charter

D.
the project management plan