Which of the following will provide the basis for estimating, scheduling, executing, and monitoring and contro

Which of the following will provide the basis for estimating, scheduling, executing,
and monitoring and controlling project work?

PrepAway - Latest Free Exam Questions & Answers

A.
Activities

B.
Milestone list

C.
Work breakdown structure (WBS)

D.
Work packages