which point of the project is the uncertainty the highest and the risk of failing the greatest?

At which point of the project is the uncertainty the highest and the risk of failing the
greatest?

PrepAway - Latest Free Exam Questions & Answers

A.
Final phase of the project

B.
Start of the project

C.
End of the project

D.
Midpoint of the project