PrepAway - Latest Free Exam Questions & Answers

A measure of cost performance that is required to be achieved with the remaining resources…

A measure of cost performance that is required to be achieved with the remaining
resources in order to meet a specified management goal and is expressed as the
ratio of the cost needed for finishing the outstanding work to the remaining budget
is known as the:

PrepAway - Latest Free Exam Questions & Answers

A.
budget at completion (BAC)

B.
earned value management (EVM)

C.
to-complete performance index

D.
cost performance index


Leave a Reply