The Process Group in which the internal and external stakeholders interact and influence the overall outcome o

The Process Group in which the internal and external stakeholders interact and
influence the overall outcome of the project is the:

PrepAway - Latest Free Exam Questions & Answers

A.
Monitoring and Controlling Process Group.

B.
Initiating Process Group.

C.
Planning Process Group.

D.
Executing Process Group.