Which of the following project documents is an input to the Control Scope process?

Which of the following project documents is an input to the Control Scope process?

PrepAway - Latest Free Exam Questions & Answers

A.
Vendorrisk assessment diagram

B.
Risk register

C.
Requirements traceability matrix

D.
Area of responsibility summary