If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?
A. One
B. Five
C. Six
D. Seven
2 Comments on “how many weeks is the expected duration of the activity?”
lolekkkkksays:
21=5+2+14
21/3 = 7
0
0
Ankit Dhingrasays:
The formula used will be
(Worst case + Best Case + 4( Most Likely))/6
21=5+2+14
21/3 = 7
0
0
The formula used will be
(Worst case + Best Case + 4( Most Likely))/6
(5(4) + 2+14)/6 = 6